Rio de Janeiro – Maracanã
Start of the construction: August 2010
Scheduled for completion: February 2013
Current stage: 62% completed
Initial estimated cost: R$ 705 million
Cost so far: R$ 808 million

Manaus – Amazon Arena
Start of construction: July 2010
Forecasted completion: June 2013
Current stage: 44% completed
Initial estimated cost: R$ 499,5 million
Cost so far: R$ 532 million

Cuiabá – Pantanal Arena
Start of construction works: April 2011
Forecast completion: December 2012
Current stage: 47% completed
Initial cost estimate: R$ 342 million
Cost so far: R$ 519 million

Porto Alegre – Beira Rio
Start of works: July 2010
Forecast completion: June 2013
Current stage: 33% completed
Initial estimated cost: R$ 150 million
Cost to date: R$ 330 million

Curitiba – Arena da Baixada
Start of works: October 2011
Forecast completion: June 2013
Current stage: 45% completed
Initial cost estimate: R$ 184 million
Cost so far: R$ 234 million

São Paulo – Estádio do Corinthians
Start of works: May 2011
Scheduled for completion: February 2013
Current stage: 48% completed
Initial Cost estimate: R$ 335 million
Cost so far: R$ 820 million

Belo Horizonte – Estádio Mineirão
Start of works: January 2010
Forecast completion: December 2012
Current stage: 78% completed
Initial cost estimate: R$ 666 million
Cost so far: R$ 695 million

Salvador – Arena Fonte Nova
Start of works: August 2010
Forecast completion: December 2012
Current stage: 70% completed
Initial Cost estimate: R$ 591 million
Cost so far: R$ 592 million

Recife – Pernambuco Arena
Start of works: October 2010
Forecast completion: July 2013
Current stage: 51% completed
Initial estimated cost: R$ 450 million
Cost to date: R$ 500 million

Natal – Arena das Dunas
Start of works: August 2011
Forecast completion: December 2013
Current stage: 30% completed
Initial estimated cost: R$ 350 million
Cost so far: R$ 417 million

Fortaleza – Estadio Castelão
Start of works: December 2010
Forecast completion: December 2012
Current stage: 87% completed
Initial cost estimate: R$ 617 million
Cost so far: R$ 519 million